§ 152.15 APPROVAL OF PLAN BY CITY REQUIRED.
   Every applicant for a building permit, subdivision approval, or a permit to allow land disturbing activities must submit a storm water pollution control plan to the City Engineer. Submitted stormwater pollution control plans must meet the provisions specified in the city’s Engineering Guidelines. No building permit, subdivision approval, or permit to allow land disturbing activities must be issued until the city approves this plan.
(Ord. 128, passed 2-8-00; Am. Ord. 1501, passed 1-27-15)