(A) As work progresses under a building permit, the holder thereof shall cause the Code Administrator to be notified when an inspection is necessary as outlined in this subchapter, namely the following.
(1) Site inspection. After structure is staked on property but before excavation is started.
(2) Footing inspection. Upon completion of the rough frame of the structure, including the application of roof shingles and sidewall sheathing and the installation of rough plumbing and chimneys and before the lath is applied.
(3) Framing inspection. Upon completion of the rough frame of the structure, including the application of roof shingles and sidewall sheathing and the installation of rough plumbing and chimneys and before the lath is applied.
(4) Final inspection. Upon total completion of the work authorized by the building permit and before occupancy.
(B) Should the permit holder fail to comply with the requirements at any stage of construction, the Code Administrator or his deputy is empowered to cancel the building permit issued and shall cause notice of such cancellation to be securely posted upon said construction, and such posting shall be considered as service upon and notice to the permit holder of cancellation thereof. No further work shall be undertaken or permitted upon such construction until a valid building permit shall thereafter have been issued.
(C) Prior to occupying a dwelling, a final inspection must be made. Occupying a dwelling before the final inspection is a violation of the Zoning Code.
(1990 Code, § 8.29)