§ 53.64 INSPECTION.
   The applicant for a building sewer permit shall notify the Building Inspector when the building sewer is ready for inspection and connection to the public sewer. The Building Inspector shall then inspect the building and plumbing construction therein and if such construction meets the previous requirements as approved in the construction permit, a sewer connection permit shall be issued, subject to the applicable provisions of other sections of this chapter.
(1990 Code, § 2.96) (Am. Ord. 586, passed 12-14-2009)