§ 14.5 TEMPORARY USE PERMITS.
   All temporary uses and structures that are required to obtain a temporary use permit by Table 14.8 shall obtain such permit pursuant to the procedures set forth in this Article. A temporary use permit shall be reviewed, approved, or revoked only in accordance with the regulations of § 14.8 below. Temporary uses must meet the requirements of the State Building Code.
   14.5.1   General requirements for all temporary uses and structures. All temporary uses or structures shall meet the following general requirements, unless otherwise specified in this Article.
      A.   The temporary use complies with all applicable general and specific regulations of this UDO, unless otherwise expressly stated.
      B.   Permanent alterations to the site are prohibited. Minor alterations are allowed, but the site must be restored to the original state at the end of the temporary use period. For temporary uses that are not continuous over the temporary use period (e.g., one day per month over a multi-month period) the site must be restored after each occurrence.
      C.   Signage shall comply with applicable provisions of Article 14.5 and Article 11.
      D.   The temporary use or structure will not violate any applicable conditions of approval that apply to a principal use on the site.
      E.   If the property is undeveloped, it must contain sufficient land area to allow the temporary use or structure to occur, as well as any parking and traffic movement that may be associated with the temporary use, without disturbing protected resources, including required buffers.
      F.   If the property is developed, the temporary use must be located in an area that is not actively used by an existing approved principal use, and which would support the proposed temporary use, including parking, without encroaching or disturbing existing buffers or required setbacks from buffers or streetscapes, open space, landscaping, traffic movements, pedestrian circulation.
      G.   Tents and other temporary structures, including temporary storage units, will be located so as to not interfere with the normal operations of any permanent use located on the property.
      H.   Off-street parking is approved by the UDO Administrator.
      I.   All inspections and permits required by applicable construction codes have been made and approved.
(Ord. passed 2-3-2021)