§ 94.18 INSTALLATION REQUIREMENTS.
   The excavation, backfilling, patching, and restoration, and all other work performed in the right-of-way shall be done in conformance with Minn. R. 7819.1100 and 7819.5000, as they may be amended from time to time and other applicable local requirements, in so far as they are not inconsistent with the M.S. §§ 237.162 and 237.163, as they may be amended from time to time. Installation of service laterals shall be performed in accordance with Minn. R. Chapter 7560, as it may be amended from time to time and these ordinances. Service lateral installation is further subject to those requirements and conditions set forth by the city in the applicable permits and/or agreements referenced in § 94.23(B) of this chapter.