(A) Permits for mining operations in all zoning districts shall be by conditional use permit only.
(B) The following conditions must be met:
(1) Submittal of a registered land survey indicating where the processing is to be done;
(2) No permit shall be granted for a period of longer than 12 months;
(3) Operations shall have direct access to an arterial road as identified in the comprehensive plan;
(4) A plan showing the route of trucks moving to and from the site in removing processed material from the site;
(5) The site shall be returned to its natural state as it was prior to mining including, but not limited to, trees (on a caliper inch basis), grasses, private roads and the like; and
(6) Any other conditions the Council deems necessary in order to protect the health, safety and welfare of the city.
(Ord. passed 12-17-2014)