1165.16 TIME PERIOD AND VALIDITY OF PLANNED UNIT DEVELOPMENT OVERLAY.
   The time period of validity for approved plans shall be as follows:
   (a)    Zoning and Preliminary Plan. Once a Planned Unit Development Overlay District is created, it may revert back to its underlying zoning designation if:
      (1)   A Final Plan has not been submitted to the Village within twelve (12) months; or
      (2)   No construction has begun pursuant to the Final Plan within twenty-four (24) months; or
      (3)   The timing of each phase exceeds the time frame stated in the Preliminary and Final Plans.
   (b)   Expiration of Planned Unit Development Overlay. If an approved Preliminary or Final Plan expires as provided above, notice of such expiration shall be recorded by the Development Director, and such approval shall be considered as having been revoked. No further zoning certificates for any structure shall be issued. The zoning regulations for the underlying district shall then apply unless and until a complete Final Plan is re-filed with, and approved by, the Village.
      (Ord. 26-2010. Passed 8-5-10.)