1117.03 APPROVAL.
   (a)   After receiving notice of the action of the Planning Commission as to the approval of the preliminary plan, the subdivider may proceed to file:
      (1)   Copies of the final map as may be required by the Commission.
      (2)   A written application for final approval.
      (3)   Cross-sections and profiles of streets and all other construction drawings related to the improvements to be constructed in the subdivision.
   (b)   The Commission shall, within three days after the filing of the final plan, transmit copies of the plan to the Village Engineer, and/or the Village Board of Health for their final study and recommendations. The cross-sections and all other construction drawings shall also be forwarded to the Village Engineer.
   (c)   After receiving a report from each of the aforementioned officials, the Commission shall notify the subdivider of any recommended changes or suggestions so that the subdivider may correct the final tracing and submit same for final approval.
   (d)   The final tracing shall be submitted at least five workings days prior to the meeting at which the plan to be considered by the Commission.
   (e)   The Commission shall take action on the final plan in the form of a tracing within thirty days after same has been officially filed; otherwise, said plat shall be deemed to have been approved. The certificate of the Commission as to the date of the submission of the plat for approval, and the failure to take action within such time, shall be sufficient in lieu of the written endorsement or evidence of approval herein required. If disapproved, the ground for disapproval of the final plan shall be stated on the record of the Commission, including the reference to the regulation violated by the plan.
   (f)   The subdivider shall be notified of the final action of the Commission, and he shall record the final plan in the office of the Recorder of Hamilton County, State of Ohio, within sixty days after the date of approval; otherwise, the plan shall be considered void. The subdivider shall immediately upon recording, furnish the Commission with photolithoprints and photostats of the recorded plat as may be required.
(Ord. 29-1967. Passed 9-7-67.)