(a) Before giving final approval to any subdivision, the Planning Commission will require that improvements as hereinafter listed are either:
(1) Constructed and in place;
(2) Assured of completion by the deposit with the Village of a certified check in an amount sufficient to construct such improvements, such amount to be determined by the Village Engineer;
(3) Assured of completion by the posting of a bond with the Village in an amount sufficient to construct such improvements, such amount to be determined by the Village Engineer. Such amount shall not exceed the cost of the improvements determined by competitive bids, and the form and surety of the bond; or
(4) By such other means that may be approved by the Director of Public Service and Safety which will assure the proper installation of the required improvements.
(b) The improvements required shall be:
(1) Street and alley grading and surfacing;
(2) Curbs and gutters, where required;
(3) Sidewalks;
(4) Storm sewers, culverts and bridges, where required;
(5) Sanitary sewers, where required;
(6) Water mains;
(7) Crosswalks, where required;
(8) Street trees should be provided but are not required; and
(9) Monuments as required by Appendix A of these Subdivision Regulations.
(c) No improvements shall be made unless and until all necessary plans, profiles and specifications therefor shall have been approved by the Village Engineer. All improvements shall be constructed equal to or better than the standards of quality as set forth in Appendix A of these Subdivision Regulations and/or as otherwise specified by the Village Engineer.
(Ord. 29-1967. Passed 9-7-67; Ord. 24-2019. Passed 12-17-19.)