Before an application is considered for rezoning any R/O District, a statement indicating the expected impact of the proposed development on the environment and public facilities including streets, schools, and utilities, and an economic feasibility study of the development, are required. The statement must include:
(A) Expected impact. An assessment of the expected impact of the project on the watershed, including ponds, streams, and wetlands;
(B) Topography. A survey of the existing topography, soil, vegetation, and habitat and how the development will affect these;
(C) Noise control. How the developer proposes to control noise, vibration, smoke, dust, and particulate matter during and after construction;
(D) Congestion. An assessment of the impact the project will have on congestion in streets and roadways in the vicinity, and the effect the development will have on schools and public utilities; and
(E) Economic feasibility. A marketing study of the economic feasibility of the proposed development, the market to be reached, and substantiation of the financial capability of the developer to complete the proposed development.
(Prior Code, § 152.157)