§ 94.30 DAMAGE TO OTHER EQUIPMENT.
   (A)   Maintenance work by city. When the city performs work in the right-of-way and finds it necessary to maintain, support, or move a registrant’s equipment in order to protect it, the city shall notify the local representative as early as is reasonably possible. The costs associated therewith will be billed to that registrant and must be paid within 30 days from the date of billing.
   (B)   Responsibility of registrant. Each registrant shall be responsible for the cost of repairing any equipment in the right-of-way which it or its equipment damages. Each registrant shall be responsible for the cost of repairing any damage to the equipment of another registrant cause during the city’s response to an emergency occasioned by that registrant’s equipment.
(Prior Code, § 96.30)