All land reclamation shall meet the following standards:
(A) The smallest amount of bare ground is exposed for as short a time as feasible;
(B) Temporary ground cover is used and permanent ground cover, such as sod, is planted;
(C) Methods to prevent erosion and trap sediment are employed;
(D) Fill is stabilized to accepted engineering standards;
(E) Final slopes for cut slopes should be a maximum of 1:1; or 100%; fill slope 3:1 or 30%; and grade or construction slope, 5:1 or 20%.
(Prior Code, § 904.14)