§ 806 Additional Requirements for Approval of Applications for Conditional Uses for Commercial Solar-Powered Generating Facilities.
   An impact analysis shall be submitted that includes the following:
      A.   Proposed design capacity of the facility.
      B.   Physical and operating characteristics of the facility.
      C.   Proposed operating schedule.
      D.   Proposal of how the energy produced is to be used.
      E.   Transmission contracts.
      F.   Alternatives.
      G.   Phasing opportunities.
      H.   Economic and environmental impacts (during both construction and operational phases).
      I.   Restrictions to public access.
      J.   Analysis of reflections to be generated (which cannot be directed at occupied structures, recreation areas, or roads).
      K.   Plans for on-site and off-site transmission lines and substations.
      L.   Details of all approvals from other local, State and Federal regulatory agencies.
(Ord. passed 10-2-2007; Ord. 173, passed 1/5/2015, § 10)