Upon completion of all public and/or private improvements prior to acceptance or approval of same by the Board of Supervisors in accordance with provisions set forth in Article 7 of this Ordinance, the subdivider or developer will furnish the Township with as-built plans for all utilities, roads, stormwater management facilities, and other public/private improvements shown on the approved plans. As-built plans for detention/retention basins and/or underground storage facilities utilized for stormwater management must be prepared and submitted to the Township Engineer for review immediately upon completion of rough grading to verify required stage/storage capacity. As-built plans for these facilities must be reviewed for compliance with stormwater management plan design requirements prior to any additional site work. As-built plans shall contain information listed in Appendix “D.”
(Ord. 163, passed 2-28-2012, § 405; Ord. 191, passed 1-8-2019)