The Township’s approval of an SWM Site Plan authorizes the regulated activities contained in the SWM Site Plan for a maximum term of validity of 5 years following the date of approval. The Township may specify a term of validity shorter than 5 years in the approval for any specific SWM Site Plan. Terms of validity shall commence on the date the Township signs the approval for an SWM Site Plan. If an approved SWM Site Plan is not completed according to Section 406 within the term of validity, then the Township may consider the SWM Site Plan disapproved and may revoke any and all permits. SWM Site Plans that are considered disapproved by the Township shall be resubmitted in accordance with Section 408 of this Ordinance.
(Ord. 186, passed 9-12-2017)