1313.14 ELECTRIC PERMIT FEES.
(a)   Application fee
$ 40.00
(b)   Plan review
   Commercial
$100.00
   Residential
$ 20.00
(c)   Services
   New (3)
$135.00
      Underground--French (1)
$ 45.00
   Sub panels--1 to 10
$ 5.00 each
   Sub panels--11 and over
$ 1.00 each
   Upgrade (1)
$ 45.00
   Reconnect (1)
$ 45.00
   Temporary (1)
$ 45.00
(d)   Alterations/repairs (1)
$ 45.00
   New circuits--1 to 10
$ 3.00 each
   New circuits--11 and over
$ 1.00 each
   Sub panels--1 to 10
$ 5.00 each
   Sub panels--11 and over
$ 1.00 each
(e)   Commercial refrigeration (1)
$ 45.00
(f)   Sign circuits (1)
$ 45.00
(g)   Pools
   Above-ground (1)
$ 45.00
   In-ground (+1) (2)
$ 90.00
(h)   Informational inspections
$ 45.00
(i)    Investigation fee
$200.00
(j)   Additional inspections
$ 45.00
(k)   Commercial 3 percent OBBS fee
based on subtotal of fees
NOTES:   1.   Permit holder is responsible for scheduling the final inspection.
      2.   Commercial permit applications must include fault current calculations and a one-line diagram.
      3.   An additional $45.00 reinspection fee may be imposed for work that was not properly installed, was not ready for inspection, had changed from the approved plans, or was not accessible at the time of the inspection.
      4.   Numbers in parenthesis indicate the number of inspections provided.
         (Ord. 06-286. Passed 7-25-06.)