§ 154.310 DECOMMISSIONING PLAN.
   A decommissioning plan shall be submitted by the applicant to the township for approval. The plan shall consist of a written description of the anticipated life of the system and facility; a description as to how the useful life of the system will be determined and who will make this determination; the estimated cost of decommissioning; the method of ensuring that funds will be available for decommissioning and restoration of the site; and removal and restoration procedures and schedules that will be employed if the WES becomes obsolete or abandoned. The plan shall also describe any agreement with the landowner regarding equipment removal upon termination of the lease.
(Ord. passed 7-12-2012, § 4.15; Ord. 19-3, passed 7-11-2019; Ord. 19-5, passed 8-8-2019; Ord. 2020-01, passed - -2020)