7-3-9: TIME LIMIT FOR COMPLETION:
All work provided under this chapter must be completed within seven (7) calendar days from the date of first excavation, unless otherwise requested and authorized on the application. All roads are to be restored to a passable and safe condition within twelve (12) hours of completion. If, within the standard seven (7) days or other time limit authorized by the city, the road cut or excavation has not been repaired as required, the city may revoke the excavation bond and cause the repairs to be made. The costs of repairs shall include administrative costs. (Ord. 09-02, 3-10-2009)