16.04.330: FEES AND DEDICATIONS REQUIRED:
Impact and other fees associated with development are required in addition to the construction of public improvements required with the development. All development and impact fees, cash bonds or other payments or dedications required of development as specified by the City shall be submitted as provided below:
 
Payment Or Dedication
When To Submit
Planning review fees
Application submittal
Engineering review fees
Prior to Planning Commission
Storm drain fees
Prior to recording if subdivision or condominium
Prior to building permit issuance if site plan or SRD
Water shares
Prior to recording if subdivision or condominium
Prior to building permit issuance if site plan or SRD
Recording fees and land or easement dedications
Document recording and prior to building permit issuance
Other impact or review fees
Prior to building permit issuance
Cash or escrow bonds for improvements
Prior to recording and building permit issuance
Cash bonds for landscaping
Prior to certificate of occupancy
 
(Ord. 2007-01, 1-16-2007)