§ 154.09 STORM WATER OUTLET PROTECTION.
   (A)   Intent. Stream banks and channels downstream from any land disturbing activity shall be protected from increased degradation by accelerated erosion caused by increased velocity of runoff from the land disturbing activity.
   (B)   Performance standard. Persons shall conduct land-disturbing activity so that the post-construction velocity of the 10-year storm runoff in the receiving watercourse to the discharge point does not exceed the greater of:
      (1)   The velocity established by the table in division (E) below, of this section; or
      (2)   The velocity of the 10-year storm runoff in the receiving watercourse prior to development.
         (a)   If conditions (B)(1) or (2) above of this section cannot be met, then the receiving watercourse to and including the discharge point shall be designed and constructed to withstand the expected velocity anywhere the velocity exceeds the "prior to development" velocity by 10%.
   (C)   Acceptable management measures. Measures applied alone or in combination to satisfy the intent of this section are acceptable if there are no objectionable secondary consequences. The Town recognizes that the management of stormwater runoff to minimize or control downstream channel and bank erosion is a developing technology. Innovative techniques and ideas will be considered and may be used when shown to have the potential to produce successful results. Some alternatives, while not exhaustive, are to:
      (1)   Avoid increases in surface runoff volume and velocity by including measures to promote infiltration to compensate for increased runoff from areas rendered impervious;
      (2)   Avoid increases in stormwater discharge velocities by using vegetated or roughened swales and waterways in place of closed drains and high velocity paved sections;
      (3)   Provide energy dissipators at outlets of storm drainage facilities to reduce flow velocities to the point of discharge.
      (4)   Protect watercourses subject to accelerated erosion by improving cross-sections and/or providing erosion-resistant lining; and
      (5)   Upgrade or replace the receiving device, structure, or watercourse such that it will receive and conduct the flow to a point where it is no longer subject to degradation from the increased rate of flow or increased velocity.
   (D)   Exceptions. This rule shall not apply where it can be demonstrated to the Town that storm water discharge velocities will not create an erosion problem in the receiving watercourse.
   (E)   Table. The following is a table for maximum permissible velocity for storm water discharges in feet per second (FPS) and meters per second (MPS).
Maximum Permissible Velocities
Material
F.P.S.
M.P.S.
Maximum Permissible Velocities
Material
F.P.S.
M.P.S.
Fine sand (noncollodial)
2.5
.8
Sandy loam (noncollodial)
2.5
.8
Silt loam (noncolllodial )
3.0
.9
Ordinanry firm loan
3.5
1.1
Fine gravel
5.0
1.5
Stiff clay (very collodial)
5.0
1.5
Graded, loam to cobbles (noncollodial)
5.0
1.5
Graded silt to cobbles (collodial)
5.5
1.7
Alluvial silts (noncollodial)
3.5
1.1
Alluvial silts (collodial)
5.0
1.5
Coarse gravel (noncollodial)
6.0
1.8
Cobble and shingles
5.5
1.7
Shales and hard pans
6.0
1.8
 
Source: Adapted from recommendations by Special Committee on Irrigation Research, American Society of Civil Engineers, 1926, for channels with straight alignment. For sinuous channels, multiply allowable velocity by 0.95 for slightly sinuous, by 0.9 for moderately sinuous channels, and by 0.8 for highly sinuous channels.
(1989 Code, § 154.10) (Ord. 1185, passed 6-14-2005; Am. Ord. 3032, passed 3-12-2024)