(A) Extensions of the sewer system shall be required when a mandatory connection is required by § 50.059 and sewer is not available to the property. The cost of the extension shall be at the developer’s expense.
(B) The Town will also make sewer extensions under authority of G.S. Ch. 160A, Art. 10. The extensions may be made following receipt of a petition from abutting property owners, or by action of the Town Council. Assessments levied under this authority may be payable over a period of up to 10 years.
(C) Failing all of the above, extensions may be made upon request to the Town at the applicant's expense.
(D) The Town may require that lines larger than 8 inch diameter or larger than otherwise required to serve the applicant be installed. In such a case, the Town will pay the difference in costs.
(Ord. 1942, passed 7-13-2021)