1170.08 COMPLIANCE WITH THE NATIONAL ELECTRICAL CODE.
   An electrical permit application for a solar energy system or systems shall be accompanied by a line drawing of the electrical components in sufficient detail to allow for a determination that the manner of installation conforms to the current adopted National Electrical Code. This engineering analysis showing compliance with the current adopted National Electrical Code shall be prepared by a registered design professional and shall be submitted at the time of application. This analysis may be prepared by the manufacturer of the solar panel provided that he/she is a registered design professional in the State of Ohio. This analysis shall be sealed according to the State of Ohio Seal law.
(Ord. 1738-22. Passed 6-27-22.)