The subdivider and all contractors working within the project shall maintain any adjacent public street free and clear of mud, dust and debris originating from the project site. Clean up activities shall be provided on a daily basis if necessary to avoid the movement of dirt, mud and other debris onto adjacent public right-of-way areas. A construction clean-off area shall be provided on the project site and indicated on the construction drawing submission identifying a designated area for construction vehicles and other equipment to be cleaned prior to entering adjacent public right-of-way areas. The failure to properly maintain the adjacent public right-of-way areas in a clean and orderly fashion may result in a violation of these Subdivision Regulations.
(Ord. 09-3306, passed 10-15-09)