(a) Soil Disturbing Activities Submitting an SWP3: The applicant shall submit two (2) sets of the SWP3, completed application, and the applicable fee to the Summit SWCD and two (2) sets of the SWP3 to the Village of Silver Lake Engineers office as follows:
(1) For subdivisions: After the approval of the preliminary plans and with the submittal of the improvement plans.
(2) For other construction projects: Before issuance of a zoning certificate by the Zoning Inspector.
(3) For general clearing projects: Prior to issuance of a zoning permit by the Zoning Inspector.
(b) Soil Disturbing Activities Submitting an Abbreviated SWP3: The applicant shall submit two (2) sets of the Abbreviated SWP3, completed application, and the applicable fees to the Summit SWCD as follows:
(1) For single-family home construction: Before issuance of a zoning certificate by the Zoning Inspector.
(2) For other construction projects: Before issuance of a zoning certificate by the Zoning Inspector.
(3) For general clearing projects: Prior to issuance of a zoning certificate by the Zoning Inspector.
(c) The Summit SWCD shall review the plans submitted under subsection (a) or (b) hereof, for conformance with current NPDES permit requirements and this regulation and approve or return with comments and recommendations for revisions. A plan rejected because of deficiencies shall receive a narrative report stating specific problems and the procedures for filing a revised plan.
(d) Soil disturbing activities shall not begin, final plat approvals shall not be issued, and zoning permits shall not be issued without an approved SWP3 or Abbreviated SWP3.
(e) A pre-construction meeting must be held with the SWCD inspector prior to earthwork activities. The developer, contractor, and engineer should be in attendance at the pre-construction meeting.
(f) SWP3 for individual sublots in a subdivision will not be approved unless the larger common plan of development or sale containing the sublot complies with this regulation.
(g) Approvals issued in accordance with this regulation shall remain valid for two years. If regulations concerning erosion and sediment control or stormwater quality change prior to the beginning of active construction, a new SWP3 may be requested.
(Ord. 15-2022. Passed 2-7-22.)