§ 155.097  APPLICATION PROCEDURES.
   (A)   An application for site plan review, plus either a preliminary or final site plan (nine copies), shall be submitted at least 15 days prior to the next Planning Commission meeting through the Zoning Administrator who will review the application and plans for completeness, then transmit them to the Planning Commission.
   (B)   An application for site plan review shall consist of the following:
      (1)   Nine copies of the preliminary or final site plan;
      (2)   A completed application form, as provided by the township;
      (3)   Payment of a fee in accordance with a fee schedule, as determined by the Township Board from time to time;
      (4)   A legal description of the entire property which is the subject of the site plan review; and
      (5)   Other materials as may be required by the Planning Commission.
(Ord. passed 7-30-2015)