The Final PAD Plan shall continue to control the PAD after it is finished and the following shall apply:
1. The Director of Community Development, in issuing a certificate of completion of the PAD, shall note the issuance of the recorded Final PAD Plan.
2. After the certificate of completion has been issued, the use of the land and the construction, modification or alteration of a building or structure within the PAD shall be governed by the approved Final PAD Plan.
3. After the certificate of completion has been issued, no change shall be made in development contrary to the approved Final PAD Plan without approval of an amendment to the plan except as follows:
a. Minor modifications of existing buildings or structures may be authorized by the Director of Community Development if they are consistent with the purposes and intent of the final plan and do not increase the cubic footage of a building or structure.
b. A building or structure that is totally or substantially destroyed may be reconstructed without approval of an amended PAD if it is in compliance with the purpose and intent of the Final PAD Plan.
4. An amendment to a completed PAD may be approved if it is required for the continued success of the PAD, if it is appropriate because of changes in conditions that have occurred since the final development plan was approved, or because there have been changes in the development policy of the community as reflected by the comprehensive plan or related land use regulations.
5. No modification or amendment to a completed PAD is to be considered as a waiver of the covenants limiting the use of the land, buildings, structures and improvements within the area of the PAD; and all rights to enforce these covenants against any change permitted by this section are expressly reserved.
(Ord. 743, passed 4-10-86)