§ 32.004   REVIEW AND ISSUANCE OF PERMIT
   (A)   The city will review each permit application to determine its conformance with the provisions of this section. Approval indicates that minimum requirements or intent are met and does not imply guarantee of performance. Based on the review of the permit application, the city will:
      (1)   Approve the permit application;
      (2)   Approve the permit application subject to such conditions as may be necessary to meet the requirements/intent of the objectives of this section, and issue the permit subject to these conditions; or
      (3)   Deny the permit application, indicating the reason(s) and procedure for submitting a revised application and/or submission.
   (B)   The city reserves the right to inspect the site prior to any construction activity in furtherance of the review process.
   (C)   The city’s approval of the permit is for general compliance with local requirements and the KYDOW general permit. The designer is ultimately responsible for the details of design of the EPSC Plan, with the property owner being responsible for implementation.
(Ord. 2012-06-07, passed 6-7-12)