(A) All violations will be identified and documented within seven (7) days of receiving compliance information.
(B) Initial enforcement responses (involving contact with the industrial user and requesting information on corrective or preventative action(s)) will occur within seven (7) days of violation detection.
(C) Follow-up actions for continuing or recurring violations will be taken within thirty to forty-five (30-45) days of the initial enforcement response. For all continuing violations, the response will include a compliance schedule.
(D) The violations which threaten health, property or environmental quality are considered emergencies and will receive immediate responses such as halting the discharge or terminating service.
(E) All violations meeting the criteria for significant noncompliance will be addressed with an enforceable order within thirty (30) days of the identification of significant noncompliance.
(Ord. 91-07-18, passed 7-18-91)