(A) A development permit shall be obtained prior to initiating development activities in any areas of special flood hazard established in § 151.007. The permit shall be for all improvements or structures including the placement of manufactured homes, fences, and fill.
(B) Any such development permit application that requires engineering analysis, calculations or modeling to establish a base flood elevation or regulatory floodway, or to demonstrate no increase in base flood elevation in an established regulatory floodway shall be considered a land use action requiring an opportunity for a quasi-judicial land use hearing.
(C) Replacement of public bridges and/or culverts located in the floodway that necessitate a “no-rise” certification are allowed through a Type I review process, provided the replacement bridge or culvert is located along a similar or parallel alignment and contributes no additional material to the floodway.
(Ord. 259, passed 3-17-2011; Ord. 286, passed 12-7-2017)