§ 32.02 ESTIMATED COST.
   (A)   Cost associated with deferred improvement agreements will be the equivalent of 25% of the City Engineer's per-foot estimate for street construction to full city standards. The cost will be applied to deferred improvement agreements as a frontage foot cost.
   (B)   The Engineer's estimate will be reviewed annually and updated as appropriate.
   (C)   The cost applied to deferred improvement agreements will be adopted by resolution.
(Ord. 175, passed 5-20-1999; Ord. 190, passed 6-1-2000)