(A) New connections will not begin until the new wastewater treatment plant is on line and fully operational.
(B) The following will be the proper sequence to proceed with sewer line construction:
(1) Receive proper notice from the town that sewer line construction may begin;
(2) Obtain sewer line construction permit from Town Hall and arrange for payment of tap-in fee;
(3) Arrange with the Inspector to inspect sewer lateral stub when it is exposed;
(4) Begin construction as per sewer line specifications;
(5) Arrange for the Inspector to inspect lines after they have been laid, before being covered;
(6) After proper approval from the Inspector cover lines with proper backfill; and
(7) Use of the sanitary sewer system now may begin.
(`93 Code, § 7-61) (Ord. 92-526, passed 4-27-92)