9-1-13: BUILDING PERMIT; FEES:
No permit as required by the Building Code shall be issued until the fee prescribed in this chapter or this Code shall have been paid, nor shall an amendment to a permit be approved until the additional fee, if any, shall have been paid.
   A.   The following fee schedule is adopted:
      1.   New construction: Based on total square footage of entire project (including basement):
         a.   Residential:
            (1)   Building Permit:
               (A)   Primary Structure: One hundred dollars ($100.00) base fee plus seven dollars and fifty cents per one hundred square feet ($7.50/100 sq. ft.).
               (B)   Garages (any allowable size): One hundred dollar ($100.00) flat fee.
            (2)   Electrical Permit:
               (A)   One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
               (B)   Garages: Twenty five dollar ($25.00) flat fee.
            (3)   Mechanical Permit: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (4)   Plumbing Permit: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
         b.   Commercial:
            (1)   Building Permit: One hundred dollar ($100.00) base fee plus twenty dollars per one hundred square feet ($20.00/100 sq. ft.).
            (2)   Electrical Permit: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (3)   Fire Alarm Permit: One hundred dollar ($100.00) flat fee.
            (4)   Mechanical Permit: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (5)   Plumbing Permit: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (6)   Fire Sprinkler System: One hundred dollar ($100.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
      2.   Major Additions Or Alterations (more than four hundred square feet (400 sq. ft.)):
         a.   Residential:
            (1)   Building Permit: Fifty dollar ($50.00) base fee plus seven dollars and fifty cents per one hundred square feet ($7.50/100 sq. ft.).
            (2)   Electrical Permit: Fifty dollar ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.)
            (3)   Mechanical Permit: Fifty dollar ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (4)   Plumbing Permit: Fifty dollar ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
         b.   Commercial:
            (1)   Building Permit: Fifty dollar ($50.00) base fee plus twenty dollars per one hundred square feet ($20.00/100 sq. ft.).
            (2)   Electrical Permit: Fifty dollar ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (3)   Mechanical Permit: Fifty dollars ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
            (4)   Plumbing Permit: Fifty dollar ($50.00) base fee plus four dollars and fifty cents per one hundred square feet ($4.50/100 sq. ft.).
      3.   Minor Additions/Alterations (less than four hundred square feet (400 sq. ft.)):
         a.   Residential:
            (1)   Building Permit: Forty five dollar ($45.00) flat fee:
               (A)   Moving a trailer (includes inspection fees);
               (B)   Patio/patio covers;
               (C)   Sheds;
               (D)   Decks;
               (E)   Carports;
               (F)   Porches;
               (G)   Windows (enlarge or escape windows).
            (2)   Curb Cut: Fifteen dollars ($15.00).
            (3)   Roof Permits: Forty five dollars ($45.00) plus one dollar per one hundred square feet ($1.00/100 sq. ft.) of roof (square feet of shingles).
            (4)   Electrical Permits: Thirty five dollars ($35.00), includes breaker box.
            (5)   New Or Replacement Electrical Service: Thirty five dollars ($35.00).
            (6)   New Or Replacement HVAC: Thirty five dollars per unit ($35.00/unit).
            (7)   Plumbing Permit: Thirty five dollars ($35.00).
            (8)   Water Heater: Thirty five dollars ($35.00).
         b.   Commercial:
            (1)   Building Permit: One hundred dollars ($100.00).
            (2)   Roof Permit: One hundred dollars ($100.00) plus four dollars per one hundred square feet ($4.00/100 sq. ft.) (square feet of shingles).
            (3)   Electrical Permit: Fifty dollars ($50.00) (includes breaker box).
            (4)   New Or Replacement HVAC: One hundred dollars per unit ($100.00/unit).
            (5)   Commercial Kitchen Exhaust Hoods: Fifty dollars ($50.00).
            (6)   Commercial Kitchen Hood Suppression Systems: Fifty dollars ($50.00).
            (7)   Plumbing Permit: Fifty dollars ($50.00).
      4.   Flat Fee Exceptions To The Above:
         a.   Building:
            (1)   Cell Towers: Two hundred fifty dollars ($250.00).
            (2)   Siding/Stucco (partial structure less than 400 square feet): Forty five dollars ($45.00).
            (3)   Siding/Stucco (more than 400 square feet): Forty five dollars ($45.00) base plus one dollar per one hundred square feet ($1.00/100 sq. ft.).
            (4)   Fence: Forty five dollars ($45.00).
            (5)   Ramp: Twenty five dollars ($25.00).
            (6)   Demolition Permits: Fifteen dollars ($15.00). Owner or contractor is required to have a one million dollar ($1,000,000.00) insurance policy for commercial or industrial structures.
            (7)   Pool (In-Ground): One hundred fifty dollars ($150.00), includes electrical and plumbing inspections.
            (8)   Pool (Above-Ground): Twenty five dollars ($25.00).
            (9)   Signs (All Sizes): Fifty dollars each ($50.00/each).
            (10)   Electrical Installation For Signs: Fifty dollars ($50.00).
            (11)   Temporary Signs (any size - thirty (30) day duration): Twenty five dollars ($25.00) each sign.
            (12)   Flatwork (non-porous, dustless surface) -- two hundred fifty (250) to nine hundred ninety nine (999) square feet: Twenty five dollars ($25.00).
            (13)   Flatwork (non-porous, dustless surface) -- one thousand (1,000) or more square feet: Fifty dollars ($50.00).
         b.   Electrical:
            (1)   Generator (Residential): One hundred dollars ($100.00).
            (2)   Generator (Commercial): Two hundred fifty dollars ($250.00).
            (3)   Solar Panels (Residential): One hundred dollars ($100.00).
            (4)   Solar Panels (Commercial): Two hundred fifty dollars ($250.00).
         c.   Plumbing:
            (1)   Lawn Sprinkler Systems: Fifty dollars ($50.00).
            (2)   Lawn Sprinkler Systems (Partial): Twenty five dollars ($25.00).
            (3)   Backflow Device: Twenty five dollars ($25.00).
            (4)   Sewer Tap: Twenty five dollars ($25.00).
            (5)   Replace Sewer Line: Thirty five dollars ($35.00) plus sewer tap fee if needed.
      5.   Miscellaneous:
         a.   Extensions Of Active Permits: Fifteen dollars ($15.00) per six (6) month extension.
         b.   Renewal Of Expired Permits: One half (1/2) the cost of the original permit.
         c.   Work Begun Before Permit Obtained: Add one half (1/2) cost of the permit fee. (Ord. 1228, 12-20-2021; amd. Ord. 1246, 10-3-2022)