(A) Reasons for denial. The city may deny a permit for failure to meet the requirements and conditions of this chapter or if the city determines that the denial is necessary to protect the health, safety, and welfare of the public or when necessary to protect the right-of-way and its current use.
(B) Procedural requirements. The denial of a permit must be made in writing and must document the basis for the denial. The city must notify the registrant in writing within ten business days of the decision to deny a permit. If an application is denied, the registrant may cure the deficiencies identified by the city and resubmit its application. If the application is resubmitted within 30 days of receipt of the notice of denial, no additional application fee shall be imposed. The city must approve or deny the resubmitted application within 30 days after submission.
(Ord. 204, passed 12-18-2018)