§ 16.238.12 TIMELINESS.
   If the Director does not take action within one year from the date the application is deemed complete, such application is considered to be approved. However, the applicant may request an extension of time up to 120 days. This time limit period is not applicable with regard to the time in which the Planning Commission or, if applicable, the City Council may act on an appeal.
(Ord. 1242, passed 5-7-12)