§ 16.110.180 NONCONFORMITY ABATEMENT – NOTICE.
   (A)   Upon determination by the Planning Director that a use on a given parcel of land is a nonconforming use and the permitted abatement period has lapsed, the Director must send a notice to the owner of the parcel, as shown on the last equalized assessment roll, identifying the requirement for abatement. Such notice must be sent by a method certifying delivery of the notice.
   (B)   The notice required by this section must state the following:
      (1)   The property in question contains a nonconforming use;
      (2)   The date the use became nonconforming; and
      (3)   The date of required abatement established in this Code.
(Ord. 1181, passed 11-19-07)