§ 16.202.030 APPLICATION REVIEW AND PROCESSING.
   (A)   Within 30 days after receiving an application for a development project, the Planning Director shall determine in writing whether an application is complete. Such a determination shall be transmitted immediately to the applicant at the address indicated on the application form.
   (B)   If an application is determined to be incomplete, the Planning Director shall specify those parts of the application that are incomplete, and shall indicate the manner in which they can be made complete.
   (C)   After the Planning Director has accepted an application as complete, the Planning Director shall not subsequently request of an applicant any new or additional information that was not required as part of the application originally determined to be complete.
   (D)   The Planning Director may in the course of processing an application, require the applicant to clarify, amplify, correct, or otherwise supplement the information required for the original application.
   (E)   Termination of incomplete application. Upon written notification to the applicant, processing of an incomplete application may be terminated if no reasonable effort has been made by the applicant to complete the application for a period of six months from the date of notification of incompleteness. All unused fees shall be refunded to the applicant. An extension to this six-month period may be granted by the Planning Director on written request by the applicant showing good cause.
(Ord. 1104, passed 7-19-04)