§ 16.96.070 TIME LIMITS AND EXTENSIONS.
   (A)   Time limit.
      (1)   Once a grading permit has been issued, the permittee must fully perform and complete all of the approved work pursuant to the grading permit within the time limit specified in the permit. Once grading has commenced, it must be pursued with diligence so as to complete the operation within a reasonable period of time.
      (2)   If there is a cessation of grading activity for a period in excess of 60 days, the city may utilize the bonds posted to guarantee performance to complete the grading. The cessation of grading activity between November 1 and April 15 due to heavy rainfall will not be cause for the city to utilize the bonds to complete the grading.
   (B)   Extensions. If the permittee is unable to complete the work within the specified time, he or she may, prior to the expiration of the permit, submit a written request for an extension of time in which to complete the work. If, in the opinion of the City Engineer or Building Official, sufficient justification is shown, the time specified on the permit may be extended for a period of up to 180 days or as approved by the City Engineer or Building Official, but no such extension will release any surety upon the bond.
(Ord. 1103, passed 3-7-05)