(A) A vesting tentative map is filed using the same form, accompanying reports, and data as a tentative map, with the following additional requirements:
(1) Identification. At the time a vesting tentative map is filed, it must have printed conspicuously on its face the words "Vesting Tentative Map.”
(2) Right-of-way. The map must show proposed street widenings and extensions; existing and proposed sidewalks and curb cuts; existing and proposed fire hydrants within 300 feet of the project perimeter; and existing utility poles.
(3) Site and buildings. Information must be provided regarding the type and use of all buildings, both existing and proposed; location of buildings to be removed; square footage of each floor, building, lot, and total project; all facilities and accessory structures related to underground utilities and street lighting; all mechanical equipment on the buildings or on the site; appropriate screening methods and materials; and the location and screening of outdoor trash and storage areas.
(4) Parking and circulation (if applicable). Information must be provided regarding the parking spaces to be provided, with total number of spaces given; wheel stops or curb substitute; parking space striping; handicap parking; ingress and egress to include all private drives; and pedestrian walkways.
(5) Landscaping (if applicable). Diagrams must be provided showing and identifying all existing trees; existing and proposed landscaped areas in terms of proposed plants by type, size, spacing, and number; screening of adjacent properties, if required; and square footage of common usable and private open space (patio) areas, where such is required by this title.
(6) Floor plans. Dimensioned preliminary floor plans must be provided for each proposed use.
(7) Building elevations, with grading. Diagrams must be provided to show two cross-section lines that clearly portray buildings and grading concepts; natural grade (dotted lines) and finished grade (solid lines); preliminary renderings of front, right side, left side, and rear elevations of all buildings; building height in feet and stories; proposed construction materials; and the proposed colors of all buildings.
(B) Through the application review process, the Director or Engineer may require that additional information be included with the vesting tentative map to provide important or necessary disclosures or other information.
(Ord. 1102, passed 6-7-04)