§ 120.031 ABANDONMENT PROCEDURE.
   A well shall be considered properly abandoned for the purposes of this code when:
   (A)   A copy of the Division of Oil and Gas “Notice of Intention to Abandon” furnished by the Division of Oil and Gas is mailed to the Building Inspector; and
   (B)   The well has been abandoned in accordance with the requirements of the Division of Oil and Gas; and
   (C)   The site has been cleared of all drilling or producing equipment and left in a clean condition, which shall include draining and backfilling of any sump used in connection with the well and removal of concrete, pipe and other foreign materials from the surface of the ground, and the surface of the land, insofar as practicable, left in a neat and orderly condition; and
   (D)   The Building Inspector shall have inspected and certified in writing that such well has been properly abandoned in accordance with the provisions of this chapter.
('81 Code, § 5.40.080)