§ 119.035 ACTION ON PERMIT APPLICATIONS - TIME FOR REVIEW.
   (A)   The Director must determine whether or not an application is complete within 21 days after the application was first submitted. If deemed incomplete, the Director must provide written notice of incompleteness to the applicant and identify what is required to make the application complete. An applicant must make corrections to the application within 21 days after receiving notice to avoid paying a new application fee. If the Director fails to provide a notice of incompleteness within 21 days, then the application is deemed complete on the date of application.
   (B)   Within 21 days after an application is deemed complete, the Director must either issue or deny a permit.
(Ord. 1123, passed 10-20-04)