§ 51.113 COMPLIANCE SCHEDULES.
   A compliance schedule required as a result of an industrial user's noncompliance with applicable federal and/or local pretreatment standards or requirements, or for the installation of technology required to meet applicable standards or requirements must be based on the following:
   (A)   A list of the expected increments of progress in the form of dates for the commencement and completion of major events leading to consistent compliance with applicable federal and/or local pretreatment standards;
   (B)   No increment referred to above exceed three months;
   (C)   Not later than 14 days following each date in the schedule and the final date for compliance, the industrial user must submit a progress report to the Director including as a minimum, whether or not the user complied with the latest increment of progress, the reason for delay, and the steps taken by the user to return to the schedule established.
(Ord. 1093, passed 2-17-04)