25.03.05: ADDITION OF SECTIONS Rl09.1.5.4, Rl09.1.5.5, and R109.1.6.3:
Notwithstanding the provisions of section 25.03.01 of this article, new sections R109.1.5.3, R109.1.5.3, and R109.1.6.3 are added to the Residential Code to read as follows:
   R109.1.5.4 Prior to frame approval, a rough zoning inspection is required in order to ensure compliance with the approved Development Plans.
   R109.1.5.5 Prior to final approval, a final zoning inspection by Planning Department staff is required in order to ensure final compliance with approved Development Plans.
   R109.1.6.3 Connections prohibited. Unless approval has been first obtained from the Building Official, the connection of gas or electrical utilities shall be prohibited until the final building, heating, air conditioning, electrical, plumbing and grading inspections, as required, are completed and approval has been granted on any building.
(Ord. 0-19-1357, 11-13-2019)