(A) The grantee shall comply with the requirements of the system construction schedule contained in the franchise agreement.
(B) Service need not be provided where power and telephone utilities are not available.
(C) The grantee shall provide a detailed construction plan indicating the progress schedule, area construction maps, test plans and projected dates for offering service. In addition, the grantee shall update such information on a monthly basis, showing specifically whether schedules are being met and the reasons for any delay.
(D) Failure to begin construction within one year after the award of the franchise shall be grounds for franchise revocation at the option of the grantor.