(A) Upon completion of the backfilling, temporary pavement material shall be used to resurface the excavated area unless otherwise specified. All temporary paving material shall conform closely enough to the level of the adjoining paved surface and shall be compacted so that it is hard enough and smooth enough for pedestrians and vehicular traffic to pass over it safely. The permittee shall be responsible for maintaining the temporary pavement.
(B) Within 30 days after completion of all backfilling, or as specified by the Administrative Authority, permanent resurfacing shall be commenced and diligently prosecuted to completion. The Administrative Authority reserves the option to place permanent pavement by its forces at the expense of the permittee.
('65 Code, § 7-3.20) (Ord. 349-C.S., passed - - ) Penalty, see § 10.99