(A) Consistency with approved plans. All landscaping shall be installed consistent with approved plans and specifications, in a manner designed to encourage and maintain healthy plant growth.
(B) Timing of installation. Required landscaping shall be installed prior to the issuance of a certificate of occupancy for the associated project.
(C) Certification of substantial completion. Upon completion of the installation of the landscaping and irrigation system, a field observation shall be completed by the landscaping professional. The landscaping professional shall submit a certificate of substantial completion to the city, utilizing forms designated for this purpose. The certificate shall specifically indicate that the plants were installed as specified, that the irrigation system was installed as designed, along with a list of any deficiencies.
(Ord. 601-C.S., passed 3-4-14)