(A) The Community Development Director shall meet with such city staff as he deems necessary to review proposed discretionary projects and make recommendations.
(B) The Application Review process, from original submittal of an application to the initial report of the Committee, shall be completed within 30 days.
(C) The City Council, Planning Commission and Design Review Commission shall be advised, in staff reports, as to the results of the Application Review recommendations for a project.
(D) Recommendations resulting from the Application Review process shall not impair the jurisdiction of the Design Review Commission, Planning Commission and City Council in their review of projects requiring discretionary approval.