§ 153.356 TIME LIMIT
   The precise plan of design or site plan review shall be valid for one year from the approval date. Construction must be commenced within one year from the approval date. If construction has not commenced within one year from the approval date, but the applicant has diligently pursued the project plan review process, the Community Development Director may extend the precise plan of design or site plan review for up to one additional year. If construction has not commenced within this additional one-year period, the precise plan of design or site plan review shall expire and no longer be valid. The Design Review Commission may, upon application and with good cause shown, extend the time limit in the case of unavoidable delay.
('65 Code, § 9-3.2507) (Ord. 449-C.S., passed 6-6-95; Am. Ord. 629-C.S., passed 10-4-16)