§ 87.08.030 Final Soils Report.
   A final soils report prepared by a registered civil engineer shall be required where a preliminary soils report was required, unless the final report is waived by the Building Official.
   (a)   Filing of Report. The final soils investigation and report shall be filed with the improvement plans.
   (b)   Content of Report.
      (1)   The report shall contain sufficient information to ensure compliance with all recommendations of the preliminary soils report and the specifications for the project.
      (2)   The report shall also contain information relative to soils conditions encountered which differed from that described in the preliminary soils reports, along with any corrections, additions, or modifications not shown on the approved plans.
(Ord. 4011, passed - -2007)