§ 85.15.120 Post Decision Procedures.
   The procedures and requirements in Chapter 86.06 (Time Limitations), and those related to appeals and revocation in Division 6 (Development Code Administration), shall apply following a decision on an application for a Temporary Use Permit.
   (a)   Condition of the Site Following Short-term Activity. Each site occupied by a short-term activity shall be cleaned of debris, litter, or other evidence of the temporary activity on completion or removal of the activity, and shall thereafter be used in compliance with the provisions of this Development Code. Performance security may be required before initiation of the activity to ensure cleanup after the activity is finished in compliance with § 86.06.050 (Performance Guarantees).
   (b)   Performance Security for Temporary Structures. Before issuance of a Temporary Use Permit the applicant shall provide performance security in a form and amount acceptable to the Director to guarantee removal of all temporary structures within 30 days following the expiration of the Temporary Use Permit.
(Ord. 4011, passed - -2007)