(a) Interim Operation of Activities Requiring a Conditional Use Permit. A Temporary Use Permit may be issued for the interim operation of any use requiring a Conditional Use Permit for a period of time not to exceed 12 months, provided the Temporary Use Permit does not authorize the construction or establishment of new permanent structures and the review authority makes the findings required for approval of a Conditional Use Permit in compliance with Chapter 85.06 (Conditional Use Permit/Minor Use Permit).
(b) Concurrent Application Filing. The Temporary Use Permit application shall be filed concurrently with an application for Conditional Use Permit, where appropriate.
(Ord. 4011, passed - -2007)